Road work ahead: Grand Haven sets street paving schedule
The resurfacing of several streets in Grand Haven is underway as part of the city’s 2025 Street Resurfacing Project.

GRAND HAVEN — The resurfacing of several streets in Grand Haven is underway as part of the city’s 2025 Street Resurfacing Project.
The project kicked off on Tuesday, April 21, with manhole removal and lowering in preparation for milling, the process of removing the existing deteriorated road surface.
Motorists can expect some inconvenience during the project, but Grand Haven Assistant City Manager and Interim Director of Public Works Dana Kollewehr asks residents for patience.
“While inconvenient, street resurfacing is necessary to lengthen the life of our roads and maintain city infrastructure,” Kollewehr said. “We thank everyone for their patience while this important work is being completed.”
Paving is scheduled to begin the week of April 28, according to a news release.
The following streets are scheduled for paving on Monday, April 28:
- Second Street (from Howard Avenue to Franklin Street)
- Fifth Street (from Franklin Street to Howard Avenue)
- Madison Street (from Despelder Street to Beacon Boulevard)
Paving will continue on Wednesday, April 30, on Robbins Road (from Moreland Street to Robbins Nest) and Griffin Street (from Pennoyer Avenue to Fulton Street). Cutler Street (from Grant Avenue to Park Avenue) is scheduled for paving on Saturday, May 3.
Support Our Work
Ottawa News Network is a nonprofit news service dedicated to providing the residents of Ottawa County with trustworthy, community-driven news. ONN treats journalism as a public good — something that enriches lives and empowers Ottawa County’s 300,000-plus residents to stay engaged, make informed decisions, and strengthen local democracy. Please consider giving today.
Additionally, milling and paving work is planned for the Beechtree bike path and the city cemetery during the week of April 28.
Temporary “No Parking, Tow-Away Zone” signs will be posted in the affected areas from 7 a.m. to 8 p.m. while milling or resurfacing is underway.
City officials indicate that through-traffic will be maintained at all locations. Residents will still have access to trash pickup and emergency services.
All road work is dependent on weather conditions, and the schedule is subject to change.
— Heather VanDyke covers northern Ottawa County for the Ottawa News Network. Contact her at newsroom@ottawanewsnetwork.org.